The short answer
When another business pays you late, the law lets you add simple interest at 8% a year above the Bank of England base rate, plus a fixed sum of £40, £70 or £100 for each late payment, depending on its size. For interest that starts running between 1 July and 31 December 2026, the rate is 11.75% a year (8% plus a base rate of 3.75% on 30 June 2026).
You claim it by sending the customer a new invoice or statement for the interest and the fixed sum. Many construction contracts set their own late-payment interest rate. If yours does, that rate usually replaces both the statutory rate and the fixed sum, so check your contract first.
General information for firms in England, Wales and Scotland, checked against the official sources on 11 November 2026. It is not legal, tax or financial advice: rules change and contracts differ, so check your own position with your accountant or solicitor before you act.
Who can charge it
The Late Payment of Commercial Debts (Interest) Act 1998 covers contracts for goods or services between two businesses, which includes public bodies. It applies to construction contracts like any other business contract: main contractors, subcontractors and suppliers can all use it. It does not cover work for consumers, so a homeowner who pays late can't be charged statutory interest. In that case, only what your contract with them says applies.
When a payment becomes late
Interest starts the day after the payment was due:
- If you agreed a payment date, it is late the day after that date.
- If you didn't, it is late 30 days after the customer gets your invoice or you finish the work, whichever is later.
There are limits on long payment terms. Between businesses, an agreed term of more than 60 days only stands if it is not grossly unfair to you; otherwise interest can run from day 60. When the customer is a public authority, interest runs from day 30 at the latest, whatever the contract says.
The Act doesn't mention the Construction Act's payment dates. On a construction contract, the cautious approach is to count from the day after the final date for payment, the last day your contract gives the payer: that is when the payment is clearly late. If your contract is unclear, ask your adviser. Our guide to payment notices and pay less notices explains those dates.
The rate
Statutory interest is 8% a year above the Bank of England's Bank Rate on a fixed reference date:
| Interest starts running | Reference date | Bank Rate then | Statutory rate |
|---|---|---|---|
| 1 January to 30 June 2026 | 31 December 2025 | 3.75% | 11.75% |
| 1 July to 31 December 2026 | 30 June 2026 | 3.75% | 11.75% |
| 1 January to 30 June 2027 | 31 December 2026 | Not yet known | 8% plus that rate |
Two things catch people out. First, the rate for a debt is set when its interest starts and then stays the same, even if Bank Rate changes later. Bank Rate rose to 4% on 5 November 2026, but that doesn't change the rate on debts already running. Second, GOV.UK's own worked example uses an old base rate, so use the table above, or the Bank of England's rate history, for today's figures.
The fixed sum for each late payment
Once interest starts, you are also entitled to a fixed sum to cover the cost of chasing:
| Size of the late payment | Fixed sum |
|---|---|
| Up to £999.99 | £40 |
| £1,000 to £9,999.99 | £70 |
| £10,000 or more | £100 |
You can charge it once for each payment. If chasing a debt costs you more than the fixed sum, for example a solicitor's letter, you can also claim the reasonable extra costs.
How to work it out
It is simple interest, worked out day by day:
- Multiply the amount owed by the rate to get a year's interest.
- Divide by 365 to get the interest per day.
- Multiply by the number of days late.
When your contract has its own rate
Many construction contracts and subcontracts set their own interest rate for late payment. If that agreed remedy is a "substantial remedy", it replaces statutory interest, and the fixed sum goes with it, because the fixed sum only applies once statutory interest is running.
The law starts from the contract's side: an agreed remedy counts as substantial unless it is too small to compensate you or to discourage late payment and it would not be fair or reasonable to let it replace statutory interest. Fairness takes in things like how strong each side's bargaining position was and whether one side imposed the term. So a modest agreed rate will often stand. Only a clause that removes interest altogether, or one that fails both tests, falls away and lets statutory interest apply. Whether your contract's rate counts is a question for your adviser; check the payment clause before you send a claim, because claiming the statutory rate when the contract rate applies can undermine your case.
How to claim it
- Send a new invoice or statement for the interest and the fixed sum, showing the original invoice, the days late, the rate and your workings. GOV.UK suggests a new invoice rather than changing the old one.
- Chase in writing, with copies kept against the job.
- Before going to court, follow the court's pre-action rules, because skipping them can cost you. For disputes under construction contracts, the pre-action protocol for construction and engineering disputes applies: the other side has 14 days to acknowledge your letter of claim and 28 days to respond, and a pre-action meeting may follow. If the customer is an individual or sole trader, the debt claims protocol gives them 30 days to reply. Take advice on which applies before you issue a claim.
- Use adjudication if the Construction Act applies to the contract. It is often faster than court, and the decision is due within 28 days of referral.
- Use the court. In England and Wales, claims up to £10,000 normally go to the small claims track, and you can claim online through GOV.UK. For claims of £10,000 or less, both sides must attend the court's free mediation, and the judge can sanction a party who doesn't take part. Scotland and Northern Ireland have their own processes.
Charging interest is your right, not an obligation. Many firms use it selectively: on slow payers, or once a relationship has already broken down.
What may change
In 2026 the government introduced the Commercial Payments Bill. It would make late-payment interest mandatory, with no contracting out of it, cap most payment terms at 60 days, ban retentions in construction contracts, and give the Small Business Commissioner new powers. In November 2026 the Bill had passed the House of Lords and was waiting for its second reading in the House of Commons. It is not law yet, and the government has said it will not apply to existing contracts. Until it is in force, the rules above apply.
Questions
Can I charge interest on a late invoice without it being in my terms?
Yes. Statutory interest applies to business-to-business contracts automatically, whether or not your terms mention it, unless the contract sets its own substantial remedy for late payment. In that case the contract's remedy applies instead.
Is the fixed sum charged per invoice?
The Act attaches it to each late debt, and GOV.UK says you can charge it once for each payment. In practice that usually means each separately payable invoice.
Does the rate change when Bank Rate changes?
Not for a debt that is already late. The rate is fixed by the reference date before interest started running, and stays the same until the debt is paid.
Can I charge a homeowner late-payment interest?
Not under this Act, which only covers business-to-business contracts. Look at what your contract with the homeowner says about late payment.
Official sources
- GOV.UK, Late commercial payments: charging interest and debt recovery
- Late Payment of Commercial Debts (Interest) Act 1998
- Late Payment of Commercial Debts (Rate of Interest) (No. 3) Order 2002 (England, Wales and Northern Ireland)
- Late Payment of Commercial Debts (Rate of Interest) (Scotland) Order 2002
- Pre-Action Protocol for Construction and Engineering Disputes
- Bank of England, Official Bank Rate history
- GOV.UK, Make a court claim for money
- GOV.UK, Commercial Payments Bill factsheet
First published 11 November 2026. Last checked 11 November 2026. If something here has changed, tell us at hello@rijo.ai and we will check it.