UK construction · Getting paid

Payment notices and pay less notices, explained

Last checked 7 min readEngland, Wales and Scotland

The short answer

On most construction contracts in England, Wales and Scotland, the Construction Act sets the payment rules. The payer must send a payment notice within 5 days of each payment due date, saying what it will pay and how it worked that out. If it then wants to pay less, it must send a pay less notice by the deadline in the contract, which is 7 days before the final date for payment if the contract doesn't set one.

Without a valid pay less notice, the "notified sum" has to be paid in full by the final date for payment. That is the sum in the payment notice or, if the payer sent none, usually the sum in your application.

Free tool: Pay less and payment notice templateFill in the figures and the notice is written for you, with the sum due and how it is worked out, ready to copy or print.

General information for firms in England, Wales and Scotland, checked against the official sources on 11 November 2026. It is not legal, tax or financial advice: rules change and contracts differ, so check your own position with your accountant or solicitor before you act.

When these rules apply

The rules come from Part II of the Housing Grants, Construction and Regeneration Act 1996, usually called the Construction Act. The payment notice rules below apply to contracts made on or after 1 October 2011 in England and Wales, and 1 November 2011 in Scotland. They cover "construction contracts": contracts to carry out construction work, to arrange for others to do it, or to provide labour for it. That includes subcontracts all the way down the chain, and since 2011 it includes contracts agreed orally, not only written ones.

Two exceptions matter most to small firms:

  • Work for a homeowner who lives there. A contract with a residential occupier, for work on a house or flat they live in or intend to live in, is outside these rules altogether. An extension for a family is not covered; the same work for a landlord or developer is. In 2026 the Court of Appeal held it was arguable that an owner who planned to live in a new house but let it out for part of the year still counted as a residential occupier (the point wasn't finally decided).
  • Some kinds of work. The Act lists operations that don't count, such as making or delivering materials and components where the contract doesn't include installing them, and installing plant and machinery on sites such as power stations, water treatment works, chemical plants and food and drink factories. Most building, civil engineering, fit-out, repair and decorating work does count.

Northern Ireland has its own, similar law, the Construction Contracts (Northern Ireland) Order 1997. This guide covers England, Wales and Scotland.

The payment timeline

Every construction contract must say how much becomes due and when, and give a final date for payment. Most standard forms set their own dates. If a contract has no workable payment terms, the Scheme for Construction Contracts fills the gaps, and these are its defaults:

StepDeadline under the Scheme
Due date7 days after the end of the payment period, or the date of your claim if that is later
Payment notice (from the payer)No later than 5 days after the due date
Pay less notice (from the payer)No later than 7 days before the final date for payment
Final date for payment17 days after the due date

So under the Scheme the payer has 5 days to send its payment notice and 10 days from the due date to send a pay less notice. Weekends count, but Christmas Day, Good Friday and bank holidays are left out. In Scotland, the payer's notice must also say what work the payment relates to. Your contract's own dates win wherever it sets them: find the payment clause and the "final date for payment", and diary every date for every application.

The payment notice

The payer, or someone the contract names such as the contract administrator or quantity surveyor, must send a payment notice no later than 5 days after each due date. It must say:

  • the sum the payer considers due at the due date; and
  • the basis on which that sum is calculated.

The sum can be zero, but the notice must still show how the payer got there. Some contracts reverse this and make the payee give the notice instead, in the same 5-day window.

If no payment notice arrives

If the payer misses its deadline, the payee can give a "notice in default" at any time afterwards, stating the sum it considers due and how it worked it out. The final date for payment then moves back by the number of days the notice in default came after the payer's deadline.

Often no extra notice is needed. Where the contract lets the payee apply for payment before the payer's notice is due, as most interim applications do, the Act treats that application as the notice in default, as long as you sent it on time and in the form the contract requires. Your application then sets the notified sum, and the final date doesn't move.

The pay less notice

If the payer intends to pay less than the notified sum, it must send a pay less notice. It must say:

  • the sum the payer considers due on the date the notice is sent; and
  • the basis on which that sum is calculated.

It must be given no later than the period before the final date for payment that the contract sets, or 7 days before it under the Scheme. The sum can be zero, for example where the payer says earlier overpayments or defects cancel out this application.

In 2026 the Court of Appeal said these notices should be read in a common-sense way, not as a tick-box exercise: the question is whether the notice explains, reasonably clearly, what is due and why. A notice that just gives a figure, with no explanation, is not enough. A notice that arrives late doesn't count at all.

If there is no valid pay less notice, the payer must pay the notified sum on or before the final date for payment. Disagreeing with the application is not enough on its own. The main exception is insolvency: where the contract says nothing is payable if the payee becomes insolvent, and the payee becomes insolvent after the pay less deadline, the payer doesn't have to pay.

What you can do if you aren't paid

If the notified sum isn't paid in full by the final date, the Act gives you three tools, and you can use them together.

  1. Suspend work. You can suspend all or part of your work after giving at least 7 days' written notice of your intention, stating the grounds. You are entitled to your reasonable costs of the suspension, and the time lost is added to your contract period. The right ends when you are paid in full. Take advice first, because a defective notice can put you in breach.
  2. Adjudication. Either party can give notice of adjudication at any time. The adjudicator should be appointed and the dispute referred within 7 days, and the decision is due within 28 days of referral, or up to 14 days later with the referring party's consent, or longer if both agree. The decision is binding unless and until a court, an arbitrator or a settlement says otherwise. Claiming an unpaid notified sum because no valid pay less notice was sent is often called a "smash and grab" adjudication. The Court of Appeal has held that a payer who missed its notices can still ask an adjudicator to value the work, but only after it has paid the notified sum.
  3. Interest and compensation. Late payment interest and a fixed sum for each payment may be added, unless your contract sets its own interest rate. See our guide to late-payment interest.

If you are the payer

Most main contractors are payers and payees at once. The same rules bind you towards your subcontractors:

  • Diary each subcontract's due date, payment notice deadline, pay less deadline and final date.
  • Send a payment notice for every application, with the calculation, even when the sum is low or zero.
  • If you intend to pay less, send the pay less notice in time, with the figures and reasons, to the address the subcontract gives for notices.
  • Don't rely on "pay when paid". A clause that makes your payment depend on being paid by your own client is ineffective, unless the client is insolvent.

What may change

The Commercial Payments Bill, in the House of Commons in November 2026, would cap the final date for payment on most construction contracts at 60 days after the due date, and ban retentions. It is not law yet and wouldn't apply to existing contracts. We will update this guide if it passes.

Questions

Is a payment notice the same as an invoice or an application?

No. An application for payment, or an invoice under some contracts, is the payee's claim. The payment notice is the payer's answer: what it considers due and why. If the payer sends none, your application can stand in its place.

Can a pay less notice be for zero?

Yes. The sum in a pay less notice can be zero, as long as the notice explains how it was calculated and arrives in time.

Official sources

  1. Housing Grants, Construction and Regeneration Act 1996, Part II (the Construction Act)
  2. Construction Act, section 110A (payment notices)
  3. Construction Act, section 110B (notice in default)
  4. Construction Act, section 111 (pay less notices and paying the notified sum)
  5. Construction Act, section 112 (suspension for non-payment)
  6. Construction Act, section 106 (residential occupiers)
  7. The Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II
  8. The Scheme for Construction Contracts (Scotland) Amendment Regulations 2011
  9. Court of Appeal, S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448
  10. Court of Appeal, RBH Building Contractors Ltd v James [2026] EWCA Civ 511

First published 11 November 2026. Last checked 11 November 2026. If something here has changed, tell us at hello@rijo.ai and we will check it.

Questions about any of this? Ask us.

A few lines is plenty. You will hear back within one working day with questions or a rough price.

Or email hello@rijo.ai Or call +44 7360 536033

What do you need?
Did a Rijo partner send you?
We reply within one working day. See our privacy notice.